9th Floor Update – 12/20/2010

 

MEMORANDUM

 TO:                  WINDSOR HOUSE 9th FLOOR RESIDENTS

FROM:            Niyi Fajana, Community Manager

RE:                   9th Floor Fire Repairs

 Date:                December 20, 2010

Please be advised, Windsor House will begin repairs on the 9th floor starting Monday, December 20, 2010 which is expected to last over the next few weeks. 

This work will be in several different phases.

 To contain the situation in unit 907.

  1. Make the hallways safe – this work is expected to take 20 working days. 
  2. Once that is complete, the work will shift into the units where we will complete a visual assessment for damage.
  3. Depending on what is found, will determine if any immediate repairs are required.  If there isn’t any damage, then your unit will need an air sample clearance test, to show no residual asbestos entered the unit during the fire.  Once the unit passes clearance, you will be allowed in to claim your belongings.
  4. Should there be asbestos contamination; the contractors will develop a schedule for clean-up. 

Approximately, we are roughly 25 working days before knowing what the conditions of your belongings are.

We apologize for the delay and appreciate your continued patience as we work through this challenging period.

If you have any questions or concerns, please feel free to contact us in the office at 202-332-1334 or email us at windsorhouse@starpower.net.

Thank you in advance.

Advertisements
This entry was posted in Uncategorized. Bookmark the permalink.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s